Lead Times: What Takes Long and What to Order First
Projects rarely fail on equipment price; they fail on schedule. A handful of items have lead times long enough to determine the commissioning date, and they are predictable.
Typical long-lead items
| Item | Typical lead time | Why |
|---|---|---|
| MVR compressor | 16–30 weeks | Custom impeller, motor, testing |
| Titanium autoclave | 20–36 weeks | Alloy supply, heavy fabrication, certification |
| Rectifier / transformer | 10–20 weeks | Copper and laminations, custom tap ranges |
| Glass-lined reactors | 12–24 weeks | Specialist lining and testing |
| Large titanium or duplex fabrication | 12–20 weeks | Welding qualification, material availability |
| Standard PP/316L tanks and skids | 6–12 weeks | — |
| Instrumentation | 4–12 weeks | Some analysers much longer |
Sequencing rule
Order by lead time, not by importance. The compressor and the autoclave should be released as soon as the process basis is frozen, even if the balance of plant is still being detailed. Everything else can be adjusted later without moving the commissioning date.
What freezes the design
You cannot release long-lead equipment without a frozen process basis: flow, duty, liquor composition, temperature and pressure. That is precisely what the pilot is for. If you are buying a demonstration plant before piloting, expect to change the specification once — and build that into the contract.
Practical buffer
Add four to six weeks for FAT, documentation and shipping, and another two to four for customs and site receipt. Buyers who plan to the supplier’s ex-works date are consistently late.
On payment terms
Long-lead items usually require a deposit at order and a progress payment at material purchase. Plan cash flow around that; a 30/70 split on delivery is not realistic for a compressor.
Tell us your target commissioning date and process basis, and we will return a schedule with the critical path marked.